The number of operations resources to be drawn on if an operations resource group is specified in the Resource requirements ...

The number of operations resources to be drawn on if an operations resource group is specified in the Resource requirements field group. The field must contain the value 1 when an operations resource is specified. If an operations resource is assigned to the operation, the system enters the number in this field. You can change the number. For example, an operation is attached to a resource group that consists of 5 operations resources. The process time for the operation is 3 hours, and 2 is specified in the Quantity field. When you run operations scheduling, 6 hours are reserved for the resource group. When you run job scheduling, 3 hours are reserved for two different operations resources.