The number of operations resources involved if a resource group is specified in the Requirement type field. When a resource ...

The number of operations resources involved if a resource group is specified in the Requirement type field. When a resource is selected, this field must contain the value 1. For example, the operation requires two resources from a resource group that consists of five machines. The process time for the operation is three hours, and 2 is specified in the Quantity field. For operations scheduling, six hours are reserved for the operations resource group. For job scheduling, three hours are reserved for two different operations resources. In the Production route page for the production, the operations resource quantity is filled in automatically with the quantity specified here. However, it can be changed for the current operation in the production route.