There is a problem with the predecessor information.}Try one of the following: \- Type only positive, whole numbers for simple ...

{There is a problem with the predecessor information.}Try one of the following:

\- Type only positive, whole numbers for simple relationships between tasks in the same project.
\- To include a dependency type and a lead time, type the predecessor ID number, dependency type, a \'plus\' sign and lead or lag time. For example: 2FS+3d
\- To create a link between tasks in different projects, type the project name, a backslash and then the predecessor ID number. For example: c:\\MyProject.mpp\\10
\- If the predecessor information is too long, use the Task Information dialog box.