Project did not reschedule certain unstarted tasks because of a constraint date applied to them. If you want to find these ...

{Project did not reschedule certain unstarted tasks because of a constraint date applied to them.  If you want to find these tasks in order to reschedule them, from the Project menu, point to Filtered For, click More Filters, select the Should Start By filter, and then enter the same date as was entered in the Reschedule Uncompleted Work to Start After date field in the Update Project dialog box. Then change the constraint dates of the filtered tasks using the Task Information dialog box.  To allow Project to reschedule the tasks for you, set the tasks' constraint type to As Soon As Possible, and try your Update Project operation again.}