Enter the number of days that are added to the requirement date for the receipt during master scheduling. Safety margins ...

Enter the number of days that are added to the requirement date for the receipt during master scheduling. Safety margins for the coverage group and safety margins for the master plan are summed during master scheduling. For example, if the receipt margin is set to 4 days and a purchase order line is scheduled for receipt on the 15th of the month, master scheduling calculates the adjusted receipt date as the 19th of the month.