The Finish Slack field contains the duration between the Early Finish and Late Finish dates. The smaller of the finish slack ...

The Finish Slack field contains the duration between the Early Finish and Late Finish dates. The smaller of the finish slack and start slack amounts determines the amount of free slack available, that is, the amount of time a task can be delayed without affecting the start date of a successor task or the project finish date.