You cannot enter a delay value here.}You cannot enter delay in the following situations: \225 On a task with an As Late As ...

{You cannot enter a delay value here.}You cannot enter delay in the following situations:  \225 On a task with an As Late As Possible constraint in a project that is scheduled from a start date.  \225 On a task with an As Soon As Possible constraint in a project that is scheduled from a finish date.  \225 On a task with a Must Finish On or Must Start On constraint.  \225 On a task that has started or is a summary or inserted project task.