The Baseline Cost field shows the total planned cost for a task. Baseline cost is also referred to as budget at completion (BAC).
The Available To field shows the ending date in which a resource will be available for work at the units specified for the ...
The Base Calendar field indicates which calendar is the base calendar for a resource calendar. The list includes the three ...
The baseline bars in this chart show the planned start and finish dates for your tasks. The scheduled bars show the dates ...
The Baseline Cost field shows the total planned cost for a resource for all assigned tasks. Baseline cost is also referred ...
The Baseline Cost field shows the total planned cost for a task. Baseline cost is also referred to as budget at completion ...
The baseline cost resource fields (Baseline1 Cost through Baseline10 Cost) store the total planned cost for a resource for ...
The baseline cost task fields (Baseline1 Cost through Baseline10 Cost) store the total planned cost for a task. The Baseline1 ...
The baseline duration fields (Baseline1 Duration through Baseline10 Duration) store the span of time planned to complete ...
The Baseline Finish field shows the planned completion date for a task at the time you saved a baseline. Information in this ...