The baseline duration fields (Baseline1 Duration through Baseline10 Duration) store the span of time planned to complete a task. The Baseline1 Duration field stores planned duration saved with Baseline 1. Likewise, the Baseline 2 Duration through Baseline10 Duration fields store planned durations for Baselines 2 through 10.
The Baseline Cost field shows the total planned cost for a resource for all assigned tasks. Baseline cost is also referred ...
The Baseline Cost field shows the total planned cost for a task. Baseline cost is also referred to as budget at completion ...
The baseline cost resource fields (Baseline1 Cost through Baseline10 Cost) store the total planned cost for a resource for ...
The baseline cost task fields (Baseline1 Cost through Baseline10 Cost) store the total planned cost for a task. The Baseline1 ...
The baseline duration fields (Baseline1 Duration through Baseline10 Duration) store the span of time planned to complete ...
The Baseline Finish field shows the planned completion date for a task at the time you saved a baseline. Information in this ...
The Baseline Finish resource field shows the planned completion date for assignments. Information in this field becomes available ...
The baseline finish resource fields (Baseline1 Finish through Baseline10 Finish) make available corresponding baseline completion ...
The baseline finish task fields (Baseline1 Finish through Baseline10 Finish) store the planned completion date for a task ...