Task \"^1\" in \"^2\" cannot be completed in the time allocated because there is a scheduling conflict between this task ...

{Task \"^1\" in \"^2\" cannot be completed in the time allocated because there is a scheduling conflict between this task and another one to which it is linked.}Try the following:  \225 Change the type of constraint on the successor tasks to As Soon As Possible or some other constraint that doesn't fix it to a specific date.  \225 Remove the link between the conflicting tasks.  \225 Shorten the duration of one of the tasks.  \225 Change the start and finish dates of one of the tasks.  \225 If the task to which \"^1\" is linked is not constrained and it is a summary task, check the constraints on the subtasks.