dates of the tasks in your schedule. A task's early finish date is the earliest date that the task could finish, based on ...

dates of the tasks in your schedule. A task's early finish       date is the earliest date that the task could finish, based       on its start date and scheduled duration. A task's late       finish date is the latest date that the task can finish       without delaying the project finish. The difference between       early finish and late finish dates determines the amount of       slack. For critical path tasks (tasks that have no slack),       the early finish and late finish dates are identical.