The approximated planned completion date for a task. When baseline is saved on a manually scheduled task without a recognized ...

The approximated planned completion date for a task.

When baseline is saved on a manually scheduled task without a recognized date value in the Finish field, Microsoft Project will estimate a Finish date of one day after the task's start date.  For all other tasks, this will be the same as Baseline Finish.