The Update Needed field indicates that changes have been made to the resource's assigned tasks. Select Publish New and Changed Assignments to update the resource.
The Unique ID field contains the number that Project automatically designates whenever a new resource is added. This number ...
The Unique ID field contains the number that Project automatically designates whenever a new task is created. This number ...
The Unique ID Predecessors field lists the unique ID numbers for the predecessor tasks on which a task depends before it ...
The Unique ID Successors field lists the unique ID numbers for the successor tasks to a task. A task must start or finish ...
The Update Needed field indicates that changes have been made to the resource's assigned tasks. Select Publish New and Changed ...
The Update Needed field indicates that changes have been made to the task since it was last published. Select Publish New ...
The URL {0} is for a Project Web Access Sharepoint Site for which you are not a valid user. If you feel you should have access ...
The user dictionary (custom.dic) cannot be updated.}The word you are attempting to add does not match the current dictionary ...
The VAC (Variance At Completion) field shows the difference between the BAC (Budgeted At Completion) or baseline cost and ...