You cannot enter a delay value here.}You cannot enter delay in the following situations: \- On a task with an As Late As ...

{You cannot enter a delay value here.}You cannot enter delay in the following situations:

\- On a task with an As Late As Possible constraint in a project that is scheduled from a start date.

\- On a task with an As Soon As Possible constraint in a project that is scheduled from a finish date.

\- On a task with a Must Finish On or Must Start On constraint.

\- On a task that has started or is a summary or inserted project task.