Select this option to override the capacity time fence for the item during master scheduling. If you select this option, ...

Select this option to override the capacity time fence for the item during master scheduling. If you select this option, enter the number of days that capacity is planned for planned production orders. Master scheduling uses the active production route for the item and schedules backward from the requirement date. If the requirement date for a planned production order is outside the capacity time fence, the lead time is determined by the delivery time of the item. The time fence is calculated forward from the current date.