Specifies the date when the item is planned to arrive in inventory. Forward calculation: planned receipt date = order date ...

Specifies the date when the item is planned to arrive in inventory. Forward calculation: planned receipt date = order date + vendor lead time (per the vendor calendar and rounded to the next working day in first the vendor calendar and then the location calendar). If no vendor calendar exists, then: planned receipt date = order date + vendor lead time (per the location calendar). Backward calculation: order date = planned receipt date - vendor lead time (per the vendor calendar and rounded to the previous working day in first the vendor calendar and then the location calendar). If no vendor calendar exists, then: order date = planned receipt date - vendor lead time (per the location calendar).