The Task Calendar field lists all calendars available to be applied to a task. This includes the base calendars (Standard, ...

The Task Calendar field lists all calendars available to be applied to a task. This includes the base calendars (Standard, 24 Hours, Night Shift) that come with Project, as well as any new base calendars you have created. When Project schedules the task, the working times in the applied task calendar supersedes those in the project calendar. If resources are assigned, the task is scheduled based on the intersection of the working times of the task and resource calendar. If you turn on the Ignore Resource Calendar field, only the task calendar is used for scheduling the task.