Project 2007
- The default value specified for the custom field is invalid. Specify a valid value from the lookup table used by the custom ...
- The default value specified for the custom field is invalid.} Specify a valid value from the lookup table used by the custom ...
- The default values for the State Lookup Table (Proposed, Approved, and Rejected) are required by the Proposals feature and ...
- The default working hours in the project will change to match the default working hours on the server.}The project contained ...
- The definition of at least one lookup table custom field has been changed so that you can only select leaf node values. Reload ...
- The deliverable has no workspace registered. The workspace may have been removed from the Project workspace settings or deleted. ...
- The deliverable you are attempting to update could not found on the SharePoint server. It may have been deleted from the ...
- The deliverables list was not found in the workspace for this project. The workspace may have been provisioned using an incorrect ...
- The dependency already exists in the project. For a given deliverable, a project can only have one dependency. Edit the existing ...
- The description for a lookup table value cannot exceed 255 characters. Specify a description no more than 255 characters. ...
- The description for a lookup value cannot contain more than 255 characters. Shorten the description, and then try saving ...
- The difference between baseline and scheduled task or resource information. Variances usually occur when you set a baseline ...
- The download is complete. To go back to the page you were originally on, click Back. You may need to resubmit the page by ...
- The drawing's horizontal or vertical distance cannot be more than ^1 ^2 from the task bar.}Type a measurement of ^1 ^2 or ...
- The Duration field is the total span of active working time for a task. This is generally the amount of time from the start ...
- The Duration Variance field contains the difference between the baseline duration of a task and the total duration (current ...
- The duration you entered is not a valid duration, or it is outside the range for this field. Type in a duration in the correct ...
- The e-mail name for the user is not valid.}The e-mail name \"^1\" is not spelled correctly, is not retrievable from the address ...
- The e-mail reminder service scans the Project Server database at the scheduled time each day, and sends e-mail messages to ...
- The EAC (estimate at completion) field shows the expected total cost of a task, based on performance up to the status date. ...
- The earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, and ...
- The Early Finish field contains the earliest date that a task could possibly finish, based on early finish dates of predecessor ...
- The Early Start field contains the earliest date that a task could possibly begin, based on the early start dates of predecessor ...
- The Earned Value Method field provides choices for whether the % Complete or Physical % Complete field is to be used to calculate ...
- The Effort Driven field indicates whether the scheduling for the task is effort driven. When a task is effort driven, Project ...
- The Email Address field contains the e-mail address of a resource. If the Email Address field is blank, Project uses the ...
- The embedded object ^1 has changed.}Do you want to save changes to the object before quitting? \225 To save any changes to ...
- The engineering department will have its own set of plans to complete the development of the product. Their involvement in ...
- The enterprise global cannot be restored.}You do not have read-write permission to the enterprise global. Contact your system ...
- The enterprise global cannot be restored.}You do not have read-write permission to the resource global, as it is also updated ...
- The enterprise global file cannot be checked out.}You cannot check out the enterprise global as it is already checked out ...
- The Enterprise Outline Code is not defined.}Enterprise Outline Code ^1 has not been defined in your enterprise global or ...
- The entire formula cannot be imported.}Combining the imported formula with the existing formula text exceeds the maximum ...
- The entity specified for the custom field is invalid. Specify a valid entity corresponding to Project, Task, or Resource. ...
- The Entity specified for the custom field is invalid. Specify a valid Entity UID corresponding to Project, Resource, or Task, ...
- The Entity specified for the custom field is invalid.} Specify a valid Entity UID corresponding to Project, Resource, or ...
- The Estimated field indicates whether the task's duration is flagged as an estimate. The Estimated field contains Yes if ...
- The evaluation committee should include members from the user community, procurement, legal, and any other involved organizations. ...
- The exception conflicts with #^1 \"^2\".}They both use the same type of exception, ^3, and their interval overlaps. Either ...
- The External Task field indicates whether the task is linked from another project, or whether it originated in the current ...
- The external task ID number is not valid.}The ID number entered for the task in the external project either does not exist ...
- The field cannot be added to the enterprise because of one of the following reasons: \225 The formula contains a syntax error. ...
- The field cannot be copied because the formula contains a syntax error or a reference to an unrecognized field or function ...
- The field has been set to roll down from the ^1field. Change the option for the ^1field to None if you want this field to ...
- The field name \"^1\" cannot be copied because \"^2\" already contains a field with that name.}Do you want to copy all other ...
- The field uses a formula or graphical indicators. To view or edit the field, you must have a newer version of the Project ...
- The field uses a formula or graphical indicators. To view or edit the field, you must have permission to use the Project ...
- The field uses a formula or graphical indicators. To view or edit the field, you must have Project Professional 2007 installed ...
- The field uses a formula or graphical indicators. To view or edit the field, you must have the Project Web Access ActiveX ...
- The field uses a formula or graphical indicators. To view or edit the field, you must have the Project Web Access ActiveX ...
- The field was successfully added to Project Server.}In order to view and use the enterprise field in the project, you will ...
- The file cannot be opened.}\225 Check that the file name and path are correct. \225 Check that the file format is recognized ...
- The file for resource pool consolidation cannot be opened.}^1 was not found. This sharer and other missing sharers (if any) ...
- The file is not a full fledged project schedule, but serves merely as a report. You can save the temporary project for future ...
- The file required for the Project Server update was not found.}The project file \"^1\" could not be located for the update ...
- The file that you want to use resources from has a different currency.}Sharing resources with a file with a different currency ...
- The file \"^1\" already exists.}To replace the existing file, click Overwrite. To choose a different name, click Cancel. ...
- The file \"^1\" cannot be found or contains a Visual Basic for Applications library that is not valid.}Verify that the file ...
- The file \"^1\" cannot be found.}While your computer was on standby, the file was moved, renamed, or deleted. Would you like ...
- The file \"^1\" cannot be opened.}\225 Check that the file name and path are correct. \225 Check that the file format is ...
- The file \"^1\" was modified while your computer was on standby.}\225 To replace the modified file with your version of the ...
- The file \"^1\" was opened read/write by another user while your computer was on standby.}\225 To open the file read-only, ...
- The file ^1 is already checked out to ^2}To save a project with that name, get ^2 to check the project back in, or contact ...
- The file, \"^1\", cannot be deleted because it is open or being used by another program.}Close the file in the other program, ...
- The files you are consolidating have different currencies.}Consolidating two files with different currencies can produce ...
- The files you are consolidating use different currencies.}Consolidating two files with different currencies can produce unexpected ...
- The filter \"^1\" cannot be found.}You tried to display a view or use an import/export map that references a filter that ...
- The Find command within one of your project's macros is missing the Field argument.}The macro that you just ran is missing ...
- The Find macro command requires a Test argument.}An example of a Find macro or toolbar command follows: Find Field:=\"Duration\", ...
- The Finish field shows the date and time that a task is scheduled to be completed. You can enter the finish date you want, ...
- The finish of task ^1 of \"^2\" is after the project finishes.}Try one of the following: \225 If you typed a task finish ...
- The Finish Slack field contains the duration between the Early Finish and Late Finish dates. The smaller of the finish slack ...
- The Finish Variance field contains the amount of time that represents the difference between a task's baseline finish date ...
- The first page number is not valid.}This is not a valid first page number or is outside the range for this field. Type a ...
- The Fixed Cost Accrual field provides choices for how and when fixed costs are to be charged, or accrued, to the cost of ...